Construction Update – February 2026

 

Seven months into the build, the Prague Gateway DC site in Jíloviště began taking greater shape, marking an important milestone in the construction process.

At this stage, the site had been almost fully cleared, levelled, and prepared for the next phases of development. Significant progress was also made on the supporting infrastructure, with the retaining walls and both the rainwater drainage and sewage systems nearing completion.

With these essential groundwork activities well underway, the project began slowly transitioning from site preparation to main construction.